Construction works are progressing well at our Clarendon Phase 3a project for St William. This phase of the development consists of four residential blocks ranging from 6 to 12 storeys. Second floor slab rebar is being fixed for the first of the four blocks, whilst the first vertical elements are going up for the second block and pilecaps are going in for the third block. The capping beam to the fourth block is being poured ahead of the top down construction of the basement. This form of construction allows for the use of a second site entry much earlier than was originally programmed, freeing up the restricted site, with PTA involved with the complex enabling and temporary works as well as the associated logistics sequencing.