PTA’s project Wembley Parade for London developer Anthology is gathering pace, now in week 28 of an overall 99 week construction program. The RC frame in the meander building is tiered from 7th – 2nd floors, whilst in the 13 storey tower the RC frame is at level 7. Most of the below ground drainage and utilities have been installed, with fit out work commencing on the lower levels on the buildings. Once completed in December 2019 the development will provide 195 high quality homes.
JULY 2018