COPPERHOUSE GREEN, DARTFORD, PHASES 1-3
CLIENT:
BELLWAY THAMES GATEWAY
ARCHITECT:
FBB ARCHITECTS
CONTRACTOR:
STATOM / KAYBRIDGE
PROJECT VALUE:
£100M
DATE COMPLETED:
Phased completion between 2022-2024
The first three phases of this residential re-generation project in Dartford provides over 550 apartments within 12 buildings, ranging from 4- to 8-storeys, as well as a new micro-brewery.
The buildings feature ground floor level undercroft parking, with RC transfer slabs over. The buildings up to 5-storeys in height comprise an RC transfer slab at 1st floor level supporting traditional loadbearing masonry construction.
The architecture features complex brickwork detailing and set-back mansard roofs.