BUILDING 84, BORDON

Work has now started with the first of 9 pours for the warehouse ground slab at Bordon. The 103,000 sqft industrial floor slab is being laid to an FM2 floor finish with DM2 finish in the defined movement areas to cater for the high-bay racking.

The project also includes 30,000 sqft of office space across 3 floors and a multi-storey steel framed car park. Due for completion in early 2023.

OCTOBER 2022